SPLOST II Notebook
SPLOST II Home
Concurrent Resolution
Additions/Modifications
Tax Analysis
Maintenance
Enrollment
C & I , Technology
Program Summary
Safety & Support
Schools
Facility Summary
|
NEW SCHOOLS
Location |
Projects |
Total I.U.s |
FACILITY TOTAL |
|
Elementary
School |
(4) |
169 |
$43,869,322 |
Middle School
|
(3) |
213 |
$66,357,170 |
High School |
(2) |
196 |
$94,539,000 |
Land |
|
|
$18,000,000 |
|
Total:
|
(9) |
578 |
$222,765,492 |
FACILITIES
Priority |
Facility Name |
Total
I.U.s |
Est.
Year of Start |
FACILITY
TOTAL |
|
001 |
Riverside Primary Elementary School
- Additional Growth - South Cobb Area |
36 |
Fall 2005 |
$9,537,353 |
002 |
West Cobb #1 High School
- 1. McEachern, 2. Harrison, 3. Kennesaw Mountain |
98 |
Fall 2006 |
$45,739,657 |
003 |
West Cobb Middle School
- 1. Lost Mountain, 2. Pine Mountain, 3. Smitha |
71 |
Fall 2006 |
$21,370,265 |
004 |
Acworth Site Middle School
- 1. Awtrey, 2. Palmer, 3. Durham |
71 |
Fall 2005 |
$19,815,465 |
005 |
Acworth Primary Elementary School
- Additional Growth - Acworth Area |
36 |
Fall 2005 |
$9,887,493 |
006 |
Austell Primary Elementary School
- Additional Growth - South Cobb Area |
36 |
Fall 2005 |
$9,226,393 |
007 |
Northwest Middle School
- 1. Durham, 2. Lost Mountain, 3. Pine Mountain, 4. Awtrey |
71 |
Fall 2006 |
$25,171,440 |
008 |
West Cobb #2 High School
- 1. Harrison, 2. Kennesaw Mountain, 3. North Cobb |
98 |
TBA |
$48,799,343 |
009 |
Northwest Elementary School
- 1. Frey, 2. Ford, 3. Vaughan |
61 |
TBA |
$15,218,083 |
|
Total:
|
(9) |
578 |
|
$204,765,492 |
|